How to Get Capstone Parts Made in 4 Weeks

Capstone teams lose time not in machining but in the steps before it: files that can't be quoted, shapes that can't be machined, and orders started two weeks before the deadline. This guide lists the sequence from design freeze to receiving parts, fitted to the semester schedule.
0. Work backward from the presentation date
| When | What to do |
|---|---|
| Presentation D‑28 | Freeze the design. Check assembly interference. Prepare the parts list (BOM) |
| D‑25 | Export STEP → get quotes. Decide material and quantity |
| D‑21 | Order and pay. Production starts |
| D‑14 | Receive parts (usually 6 days after payment). Identify assembly issues and fixes |
| D‑10 | Reorder corrected parts (2nd round) |
| D‑3 | Receive the 2nd round. Final assembly |
The key is to build the 2nd order into the schedule. On the first assembly, at least one hole position is usually off.
1. Save in a file format that can be quoted
Screenshots, PDFs, and JPGs cannot be quoted, because they contain no geometry data. Export from CAD as STEP (.step/.stp). For sheet metal parts, DWG is also accepted.
- Fusion 360: File → Export → STEP
- SolidWorks: Save As → STEP AP214
- Inventor: Export → CAD Format → STEP
- Don't upload the assembly as one file; upload one file per part. Quotes are produced per part
2. Shape decides the process
| Part shape | Process | Default material |
|---|---|---|
| Thin plate + holes (base plate, cover) | Laser cutting | AL5052 (5052 aluminum) 2 to 3T, SS400 (mild steel, similar to ASTM A36) |
| Bent-plate brackets and cases | Laser + bending | AL5052 |
| Thick blocks, pockets, precision holes (housings, mounts) | CNC milling | AL6061 |
| Shafts and cylinders (shafts, bushings) | CNC lathe | S45C (1045 carbon steel), AL6061 (6061 aluminum) |
If the decision is hard, upload the drawing and get quotes for both processes to compare. Even the same bracket is often more economical as sheet metal than as CNC.
3. Typical items where team budget is wasted
- Quantity of one, ordered many times — order the same part together in one go. Setup cost is incurred only once
- Excessive tolerances — ±0.01 often doesn't matter. Give tolerances only at fit areas and use general tolerance for the rest
- Unnecessary finishing — anodizing is for appearance and corrosion resistance. Skip it for internal parts in a demo
- Unnecessary 7075 — if the strength calculation doesn't require it, use 6061. Both machining and material cost are lower
4. Ordering, payment, and receiving
MakeIT accepts orders from a quantity of 1 and from 10,000 KRW, with payment by card or bank transfer. Delivery after payment usually takes 6 days. If one team representative creates the account, puts all parts in the cart, and pays once, delivery also arrives in one shipment. If there is a problem with a drawing (unmachinable shape, thickness mismatch), a review request arrives before production, so provide a phone number where you can be reached.
Frequently asked questions
Can an individual student sign up and place an order?
Yes. With a personal account you can check quotes and place orders.
Should we choose 3D printing or metal machining?
Parts that take load or have shafts and bearings assembled should be metal machined; mockups for checking appearance suit 3D printing. The decision criteria are set out in the 3D printing vs CNC article.
Can we get a quote with only a sketch and no 3D drawing?
A quote needs a STEP file. If no one on the team handles CAD, modeling it yourself with a Fusion 360 educational license is the fastest way.
Summary
Freeze the design 4 weeks before the presentation, save by part as STEP, use laser for plates and CNC milling for blocks, default to 6061, and reserve the 2nd order in the schedule in advance. Keep these five things and you can avoid postponing the presentation because of manufacturing.